Current Status
Build Phases
Donators

 PHASE 1

Preliminaries & groundwork
New pre-fab building including air-con, timber flooring, and connection to main building
New access ramp
Remove disabled toilet and fit new toilet in existing electric cupboard, build new electric cupboard & create passageway to new building

PHASE 2

Replace ceiling and lighting in main reception area

PHASE 3

Build counselling room and store in existing yoga room

PHASE 4

New toilet at chamber end of the existing building

PHASE 5

Replace external doors

PHASE 6

Roof insulation

PHASE 7

Change existing access ramp to opposite direction

PHASE 8

Refuse store

PHASE 9

Paint exterior

 

Notes:

Currently we have included VAT on all phases, we are investigating the possibility that we can claim exemption from VAT.

We have also included a contingency element to our costings.

Phases 2 to 9 can be done as and when we have the funds and in whatever order we choose.

We could use local contractors for Phases 2 to 9.